NIST Central Utility Plant (CUP) Compressor Upgrade

A compressed air capacity upgrade was executed without service interruption to support expanding research operations at NIST.

Client(s): National Institute of Standards and Technology (NIST)

Sector: Mission Critical

Location: Boulder, CO

Status: Completed 2013

Delivery Method: Firm-Fixed-Price (Lump Sum)

This project involved a large-scale mechanical upgrade to the Central Utility Plant serving the National Institute of Standards and Technology (NIST), driven by increased system demand associated with the addition of the new PML building. The scope included the installation of four new 100-horsepower air compressors and associated air dryers, along with all required mechanical piping, electrical infrastructure, controls integration, and system accessories.

A critical constraint of the project was maintaining uninterrupted compressed air service to occupied research facilities throughout construction. To meet this requirement, the upgrade was carefully phased so that only one existing compressor was taken offline at a time. All system outages were planned well in advance in coordination with NIST personnel, with strict outage windows established to protect ongoing scientific research. Although a four-hour outage window was allotted, the team successfully brought the new system online in approximately two hours through precise sequencing and subcontractor coordination, resulting in zero service disruption.

Given the secure and highly sensitive nature of the NIST campus, extensive communication and scheduling flexibility were essential. Shutdowns involving non-potable water, electrical systems, and controls required multi-week notification periods and frequent rescheduling based on research priorities. Sky Blue Builders maintained continuous coordination with contracting officers, site safety staff, engineers, and facility stakeholders, providing daily updates and conducting walkthroughs to ensure transparency and alignment throughout installation.

The physical installation of the compressors required detailed logistics planning due to their size and weight. Each 7,000-pound compressor was lowered into the basement through a trap door using a specialized hoisting system designed and executed by a certified hoisting contractor. Rigging operations were carefully sequenced to safely place each unit onto concrete pads without impacting adjacent systems. The project demonstrates Sky Blue Builders’ ability to deliver complex, mission-critical utility upgrades in occupied federal facilities through disciplined planning, technical expertise, and collaborative execution.